Public Relations Capital Improvement Project Status
 
Status Updated: August 2008 Project Number: 06-055-001
Current Phase: Construction

Contract Amount:  $2,273,195.00

Contractor: Hunter Contracting Co.
Contact Name:
 Tony Roach
Phone:
(602) 359-2469

Estimated Completion: 150 Days (November 2008)

Traffic Update:  The contractor will maintain access to all driveways with only temporary restrictions as needed to complete their work. 
Description:  The contractor will be installing approximately 11,000 LF of a 30-inch water line on McKellips Road from Val Vista Drive to Higley Road.