Engineering -
Public Relations Capital Improvement Project Status
 
Status Updated: October 2008 Project Number: 04-858-001
Current Phase: Construction

Contract Amount:  $4,000,000.00

Contractor:   Achen-Gardner Engineering, LLC
Contact Name:  
Fred Vidaure
Phone:
(480) 940-1300

Estimated Completion:  130 Days (October 2008)   

Traffic Update: Expect night time lane restrictions on Horne from Southern Avenue to Main Street. This will allow the contractor to re-line the wastewater pipes.
Description:   The work will include re-lining the wastewater pipes in the following five locations throughout the City of Mesa:
  • Extension Road between Southern Avenue and 2nd Avenue

  • Broadway Road between 48th Street and Recker Road

  • Power Road between Broadway Road and Arbor Avenue

  • Horne Road between Southern Avenue and Main Street

  • Southern Avenue from west of Horne Road to west of Stapley Drive